To guarantee progress, and flexibility of programme we have developed a delivery method which utilises working zones. By creating between 5-8 simultaneous constructions civil teams, working with multiple district heating installation teams we can ensure constant progress and should there be a delay in one zone, the team can move to another and works continue.
This in-house expertise extends to our pre-fabrication department, based in Blackburn, which produced the 5 customer interface connections with plans to produce more for the next phase. By undertaking this in house we have maximum control over the quality, scheduling, timing of delivery and it also brings the added bonus of reducing hot works on site, which brings multiple health and safety benefits.
In addition to the below-ground pipework we also installed the primary above ground district heating pipework to the plate heat exchangers and the above ground secondary pipework from the plate heat exchangers to the connection points on the building’s heating and hot water systems. In total we installed packaged customer heat substations and associated ancillary plant work to 4 locations with a further 4 planned for the future phase.