The project timescales were determined by an innovative procurement strategy which involved an OJEU (Official Journal of the European Union) notice leading through pre-qualification to a 2-stage tender process.
This was comprised of a 12 week preconstruction services agreement before entering into a 12 month construction programme.
The innovative tender, design and construction approach led to a 30% reduction in the project timescales, and ensured savings in floor space. Equipment specifications were complimented by future proofing the energy centre with space for a CHP and dry air cooler installation.
Collaboration throughout the tender process resulted in a fast track 2nd stage programme and we were able have heat available to the academic and residential buildings to commence commissioning in late 2017.
The timescale of the project proved to be challenging, but as we have one of the largest in-house district heating teams in the UK, we were able to allocate additional labour to the project to ensure we met the university’s heat and power on dates.